Japantown Peace Plaza Renovation | Construction update, May 2026

Rec Park Improvements: Japantown Peace Plaza Posted on May 15, 2026

Night Work:

  • Night work starts again on May 20 and will continue intermittently throughout May and June. Weeknight work hours are 11 p.m. to 7 a.m. from Monday evening through Saturday morning.
  • Expect the most noise from this round of night work over the four-day period from the night of May 26 through the morning of May 30.
  • The work consists of leveling the mall entrance finish floor, preparing for waterproofing, then reassembling the temporary walkways before the mall opens at 8:30 a.m. Night work should not impact any mall businesses nor neighborhood festivities.

Plaza/Pagoda Work:

  • The pagoda scaffolding is coming down! Over the next 7-10 days (including this Saturday, 5/16), the scaffolding will be dismantled and stacked on site to off haul mid-week.
  • The copper roofing on the Pagoda is complete and passed all inspections. For the next month, observe the soft orange glow reflected on the ceiling above before the copper patinas to its final historic color. See attached photos.
  • Pagoda painting is approximately 90% completed. Plaza painting will start in approximately one month.
  • Waterproofing work on the plaza continues. We expect some odor during this process, and fans will be in use to help with airflow.
  • Check out photos of the light and dark tile mockups used to confirm workmanship and the anticipated finish throughout the plaza.

Garage Work:

  • Plumbing/Electrical layout and installation continues.
  • 60 parking spots under the Pagoda, in both upper and lower garage levels, will be occupied through mid-2026. Drive cautiously in the garage and follow posted detours signs on both upper and lower levels. Please do not walk on the ramp between levels.

Access to and throughout Japan Center Malls and Garage:

  • Access from Geary Boulevard: Use the Geary Boulevard parking garage to access both East Mall and West Mall.
  • Access from Post Street: Use the new posted detours into East Mall adjacent to U.S. Bank and to West Malls adjacent West Mall building.
  • Sidewalk: Accessible pedestrian detour is open along the north side of Geary between Laguna to Buchanan Streets. For safety, follow all detours, stay within fenced pedestrian detour lane, and avoid walking in the bus lanes.

💬 Have questions or concerns? 

Feel free to contact the project manager:


J. Marien Coss

📧 marien.coss@sfgov.org

📞 628-652-6647


Please visit the project webpage at:

Japantown Peace Plaza Renovation Project


Japantown Peace Plaza construction May 2026 - pagoda copper glow

Japantown Peace Plaza construction May 2026 - Pagoda Copper flashing at center beam

Japantown Peace Plaza construction May 2026 - Pagoda Copper Roof northwest

Japantown Peace Plaza construction May 2026 - Tile mock up light dark